Green Valley (Khilkhet) Housing Project-1

The society's largest active housing scheme, centered on land acquisition, registration, roads, utilities, schools, lake development, and perimeter security.

Green Valley (Khilkhet) Housing Project-1
housing
Active development and land regularization
Location
Under Khilkhet Police Station, adjacent to the 300 Feet Road, Dhaka
Category
housing
Current Status
Active development and land regularization
Completion
--

Overview

The total land area of the Khilkhet Housing Project is approximately 314.47856 bighas. The society has purchased and mutated 232.82778 bighas in its own name.

The layout includes 9.05469 bighas of khas land, 7.01636 bighas of Union Parishad and Court of Wards land, and 65.57972 bighas that still need exchange or purchase. Early action is needed to exchange and register the remaining land in the society's name.

The project is progressing across several areas, including plot registration, model mosque construction, internal roads and drainage, DESCO electricity infrastructure, water supply planning with Dhaka WASA, school establishment, lake excavation, and a proposed security wall with a July Memorial plaque.

Key Facts

Total land area
Approximately 314.47856 bighas
Land mutated in the society's name
232.82778 bighas
Union Parishad and Court of Wards land
7.01636 bighas
Recently active exchange with Bashundhara Group
0.5892 bighas
Registration phase dates
16.07.2025, 20.07.2025, and 10.08.2025
Installed DESCO poles
154 poles installed so far
Land purchased by the society
232.82778 bighas
Khas land inside the layout
9.05469 bighas
Land still needing exchange or purchase
65.57972 bighas
Registered unencumbered plots
67 of 172 plots in two phases
Internal road DPP approval
BDT 49.7540 crore approved by ECNEC on 09 November 2023

Project Gallery

Milestones

  • Land registration completed for 67 unencumbered plots in two phases during July and August 2025.
  • Base type-1 work on the connecting road from the 300 Feet Road has been completed; carpeting remains pending.
  • The project has been included in the proposed Expanded Dhaka City Water Supply Resilient Project of Dhaka WASA.
  • Model Mosque construction by the Islamic Foundation is in progress on 51.33 decimals, with roof rod binding ongoing.
  • The Ministry of Primary and Mass Education sent a follow-up letter on 05.02.2025 regarding an aesthetically designed primary school in the project area.
  • Soil tests for the internal lake have been completed after site visits by Water Development Board engineers.

Open Items

  • Exchange and register the remaining 65.57972 bighas included in the project layout.
  • Complete carpeting of the connecting road from the 300 Feet Road.
  • Prepare and submit the relevant DPPs for lake, riverbank, canal, and protection works through the proper ministries.
  • Construct the proposed eastern security wall with a July Memorial plaque after estimate finalization.

Status Note

No verified percent-complete figure is available for this project, so progress is presented descriptively rather than as a progress bar.